Select Page

Pipelines

Desert Water Agency’s system is made up of about 425 miles of pipeline, but currently, has about 80 miles in need of replacement. This was a major cost driver for the agency and made rate increases unavoidable. We will now be able to generate the funds necessary to help keep our water system healthy. DWA plans to install about 3 miles of new pipe a year until at least 2031.

Some of DWA's pipelines were installed before the Great Depression!

Our team has identified the areas in most critical need of replacement and developed a schedule to start replacements. Most of the work will be done in summer months to avoid traffic. We are coordinating with the City of Palm Springs to help reduce project cost and inconvenience for our community.

While we understand that the installation of new water facilities causes an inconvenience, it is an essential part our responsibility to provide clean, reliable water to you and your neighbors.

We will update this page with new pipeline projects as information becomes available. Check back for more details.

For more information on pipeline replacement, email outreach@dwa.org or call (760) 323-4971, ext. 184.

 

2025 Pipeline Replacement Projects

The next series of pipeline replacement projects began in January 2025. Work will continue in phases through approximately early October. Schedules and end dates are subject to change based on unforeseen circumstances, such as weather, materials or utility conflicts. For more information, contact Associate Engineer Adrian Biggs at abiggs@dwa.org or 760.323.4971, ext. 193.

 

Movie Colony East – N. Calle Rolph & E. Paseo El Mirador
The pipeline replacement project in Movie Colony East on N. Calle Rolph and E. Paseo El Mirador will begin the week of Aug. 4, 2025. However, DWA crews may be on site a week early for prep work. Construction is anticipated to be complete at the end of September or early October 2025.

DWA will be flushing newly installed water mains on Wednesday, August 20. The pipes are flushed to disinfect them before use. People may notice water flowing beginning at 8 a.m. on E. Paseo El Mirador, N. Sunrise Way and E. Tachevah Drive. Most of the water will flow down N. Sunrise Way. Sandbags will be used to direct the water, which will eventually enter the city storm drain system. Signage will be placed on each of the major roadways. Traffic should be able to pass through during the flushing.

To learn more about this project and get ongoing updates, click here.

 

Historic Tennis Club & Downtown Area
The Historic Tennis Club & Downtown Area project started in April around Arenas Road, W. Baristo Road and S. Belardo Road near downtown, including portions of the Historic Tennis Club area. All mainline work is expected to be complete by the end of July. Sidewalk and concrete repairs are also expected to be complete by the end of July. Final pavement repair is scheduled for mid-August. To learn more about this project and get ongoing updates, click here.

 

Racquet Club Estates
The Racquet Club Estates project began the second week of January around E. Simms Road and N. Sunnyview Drive. Work is anticipated to be complete in June. All mainline work is now complete. Crews will conduct final pavement repair in mid-August. 

To learn more about this project and get ongoing updates, click here.

 

 

2024 Pipeline Replacement Projects

E. Via Altamira – Complete
For more information on this project, click here.

Sunmor Estates – Complete
For more information on this project, click here.

N. Sunrise Way, E. Amado Rd., E. Tahquitz Canyon Way & N. Sunset Way – Complete
For more information on this project, click here.

S. Broadmoor Dr. & E Waverly Dr. – Complete
For more information on this project, click here.

E. Sunny Dunes Road & Calle Santa Cruz – Complete
For more information on this project, click here.

Ramon Road Frontage – Complete
For more information on this project, click here.

Avenida Caballeros – Complete
For more information on this project, click here.